Mountain 1st Neighborhood
The
purpose of this project is to develop a comprehensive phased improvement plan
for the Mountain/First Neighborhood which utilizes landscape design solutions
to establish a coherent neighborhood identity and to addresses the
neighborhood’s specific concerns regarding traffic mitigation, public area
aesthetics, and pedestrian circulation. Site Inventory & Analysis (3 weeks –
estimated completion 06.10.04)
product: graphic
and textual representation of inventory data and resulting design implications (5MB .pdf) Project Goals & Objectives (1 week –
est. completion 06.17.04)
product: project goals and objective statement Community Review and Input
(06.17.04)
Preliminary Master Plan Design (4 weeks
– est. completion 07.08.04)
product: rendered master plan design drawing and supporting
illustrative details and sketches Community Review and Input
(07.15.04)
Final Master Plan & Project Report
(4 weeks – est. completion 08.05.04)
product: project report illustrating final master plan and
supporting documentation Community Review and Input
(08.19.04)
|